Capstone: lead a quarter-long project

Monday, 9:00. Companies email StayHub about 600 times a quarter asking for blocks of rooms; the median quote takes 4 days and a third never get one. Karim gives you 13 weeks, three squads and their agents. Lina says one sentence: "You lead this one."

One whole quarter, three squads, agents writing the code. You lead it from the first number on the page to the last lesson learned.

30 min advancedLeading a project end to end: goal, decisions, plan, rules, delivery, launch, learnGo / no-go launch decisions from evidenceProject retrospectives that change how the team worksArchitecture decision recordsStatus updates that say what matters (outcome, risks, decisions)Running a risk register (likelihood, impact, owner, trigger)
  1. Problem

    Companies and event organisers ask StayHub for blocks of 10 to 60 rooms by email. About 600 requests a quarter go to three people in Sales; the median quote takes 4 days and a third of requests are never answered. Karim gives you one quarter, three squads and agents to fix it.

  2. Why the simple system fails

    Starting with code (or with the agent's 20-minute architecture) skips every decision that makes a quarter succeed: the measurable goal, the irreversible choices, the order of slices, the rules for a dozen parallel agent sessions, what "ready to launch" means, and how the team learns afterwards.

  3. Engineering concept

    Run the whole leadership loop, each stage leaving evidence: goal as numbers and drivers; ADRs for one-way doors after a spike; a plan of vertical slices starting with a walking skeleton; short enforced rules; parallel delivery capped by review capacity behind required gates; a go/no-go with criteria written in week 1; incident response; a blameless retrospective with owned actions.

  4. Technology

    One-page project brief, ADRs, a spike, milestones and agent-sized tasks, root and per-directory CLAUDE.md, hooks and permission settings, branches or worktrees per session, required CI checks, feature flags and a ramp, a risk register and weekly status, runbooks, a retrospective.

  5. Trade-offs

    Every stage costs time the quarter doesn't seem to have; each skipped stage moves its cost to launch week. Scale ceremony to risk: heavy on one-way doors (inventory, money, personal data), light on two-way doors. Cut scope before checks, and let review capacity, not agent count, set the pace.

01

The problem

2 min
Monday, 9:00. A new quarter; the same 8 engineers in 3 squads.
  1. Maya · Product manager
    Companies email Sales for blocks of 10 to 60 rooms, about 600 a quarter. Median quote: 4 days. A third never get one.
  2. Karim · CTO
    You have 13 weeks. I want companies booking groups and getting one invoice a month.
  3. You · Engineer at StayHub
    Claude Code already drafted an architecture: a groups microservice, its own database, an event bus.
  4. Lina · Senior engineer, your mentor
    You lead this one.
02

The big idea

4 min
The last episode: your quarter
The big idea

Agents are strong porters; you choose the route: goal, one-way-door decisions, plan, enforced rules, launch criteria and what the team learns.

The expedition leader agrees the goal, scouts the dangerous pass, plans the camps, sets the rope rules, decides at the last camp whether to push for the summit, and runs the debrief. Every stage of this module, on one quarter.

03

How it works

5 min
The leadership loop, each stage leaving evidence
  1. 1
    Brief

    Goal: 80% of requests quoted within 1 business hour; 150 companies invoiced monthly. Drivers, non-goals, and criteria written in week 1.

  2. 2
    Spike + ADRs

    Measure the (inventory holds, invoices) before deciding; record each decision with a "revisit if".

  3. 3
    Plan

    Walking skeleton in week 3, then vertical slices with ranges; pilot in week 7.

  4. 4
    Rules + gates

    Per-directory CLAUDE.md, hooks and CODEOWNERS on risky paths, required checks with no bypass, sessions capped by review capacity (~120 PRs a week).

  5. 5
    Deliver, report, launch

    Weekly status on outcomes and risks; go/no-go checked by named people; ramp 30% → 60% → 100%.

  6. 6
    Learn

    A is a blameless look back that ends with owned, dated changes to rules, tools or templates.

04

Watch a decision being made

4 min
Worked example

Your quarter, week 1 to week 13 (Lina checks each stage)

Take group bookings from Maya's numbers to a measured result with three squads directing Claude Code.

  1. 1Spike, then ADRs

    Two days: 60-room, 7-night holds work up to ~2,000 held nights per hotel; search p95 118 → 121 ms; only a scheduled job releases holds (into the risk register). ADR-052: a groups module with an import-boundary check, not a microservice. ADR-053: invoices through the pinned chain-invoicing seam.

    Why: The agent's architecture was research; measurements and drivers made the decision.

  2. 2Rules that hold

    Holds in src/inventory are stop-and-ask, with CODEOWNERS and a hook. Week 6: a session tried to "optimise" hold queries there; the hook stopped it.

    Why: Text is guidance; enforced rules survive forty sessions a day.

  3. 3Slip handled by scope

    Week 5, one week behind. Keep the 2-session cap, move multi-city requests after the pilot, add contract tests. Pilot on time in week 7, slip reported Monday.

    Why: Scope moved; gates didn't.

  4. 4Go/no-go, result, retro

    Week 10: 74% quoted in 1 h (≥ 70%), zero invoice differences, kill switch rehearsed, no on-call owner: no-go one day, owner named, go. Week 13: 76% (target 80%), 164 companies, zero differences. Three retro actions with owners.

    Why: Week-1 criteria weren't bent, and the honest number is reported as it is.

The whole thing in one line: Measured goal, decisions from a spike, slices from week 3, enforced rules, delivery within review capacity, launch on week-1 criteria, an honest result and owned changes.
05

In real life

3 min
Separate services, or one app with boundaries?

Amazon: two-pizza teams

  • Small teams own services
  • Deploy independently
  • More services to run

Team independence, paid for in operations.

Shopify: modular monolith

  • One main app
  • Components with enforced boundaries
  • One deploy to run

Shared app, protected by boundaries.

06

What goes wrong

3 min
Adding agent sessions to catch up

Review capacity is the bottleneck.

Instead

Move scope, keep gates, add automated checks.

A silent job guarding a one-way door

Jobs stop without anyone noticing.

Instead

Read-time checks, heartbeat alerts, a rehearsed kill switch.

Retros that end with "be careful"

Nothing changes.

Instead

Owned, dated actions that change rules, tools or templates.

07

Trade-offs

3 min
ApproachFits whenYou pay
Full loop, scaled to riskMulti-team projects touching inventory, money, dataWeeks 1–3 feel slow
More agents to go fasterFree reviewers, independent tasks, strong gatesReview overwhelmed; rubber stamps
Freeze and slipThe slip is in a one-way door that can't be cutTrust and commitments spent
Week 5, Thursday, 16:00. Quote approval is a week behind; the pilot is due in week 7.
  1. Karim · CTO
    Each engineer runs five Claude Code sessions instead of two. We catch up in a week.
  2. Omar · On-call SRE
    And who reviews all that? Freeze, harden, slip the pilot to week 8.
  3. Karim · CTO
    The pilot companies are booked for training in week 7.
08

Your job as tech lead

4 min

Claude Code can write the code for this. You still own the decisions, and you have to know what good looks like to accept or reject its work.

Decisions you own
  • The goal as numbers, drivers, non-goals and go/no-go criteria, written in week 1 and agreed.
  • Every one-way door decided from a spike's measurements and recorded in an ADR with a "revisit if".
  • The order of work, how many sessions run at once, and go, no-go or wait at each ramp step.
Tell Claude Code
Read docs/projects/group-bookings/brief.md, docs/adr/052-groups-as-module.md, CLAUDE.md and src/groups/CLAUDE.md. Plan mode, don't edit: propose the week-3 walking skeleton, one request becoming a quote, a hold and a confirmation for one hotel in staging, behind the groups flag. Flag anything in src/inventory or src/billing. Then split the rest into vertical slices with criteria, size ranges and dependencies. Don't choose their order.
Check before you accept
  • The skeleton really goes request → quote → hold → confirmation, not one finished layer.
  • Slices fit review capacity: PRs a week they imply vs what reviewers can do.
  • At go/no-go, every week-1 criterion is checked by a named person; none quietly lowered.
Red flags
  • A plan ordered by layer, nothing end to end until late.
  • "Run more sessions" as the answer to a slip.
  • Go/no-go criteria edited in launch week to match the numbers.
09

Check yourself

2 min
Q1/3Scenario
Day one of the quarter. Claude Code has drafted a full architecture for group bookings in 20 minutes. What's your first move?
How confident are you?

That's the last episode, and there's no next one: your own project is. Tomorrow morning, write its goal as a number on one page, name its one-way doors, and lead.

Finished?

Mark it complete to update your skill map.

Go deeper (optional)You don't need this to understand the lesson. Open it when a project needs the details: Technical deep dive, Visual diagram, Analogy, Why it matters, Check your understanding, Practice ladder, Explain it yourself.
10

Technical deep dive

What each stage caught
Worked example

Group & corporate bookings, week 1 to week 13 (you lead; Lina checks)

Take group bookings from Maya's numbers to a measured result in one quarter, with three squads directing Claude Code, and keep the evidence each stage requires.

  1. 1Brief: goal, drivers, criteria

    Goal: 80% of requests quoted within 1 business hour (today: median 4 days); 150 companies invoiced monthly by week 13. Drivers: holds are a one-way door; invoices reuse the pinned chain path; ~120 reviewed PRs a week. Non-goals: travel policies, event spaces, card payment. Go/no-go criteria written now.

    Why: Lina's check: "Could anyone argue about whether you succeeded?" With numbers and criteria, no.

  2. 2Spike, then ADRs

    Two days on a throwaway branch: 60-room, 7-night holds work up to ~2,000 held nights per hotel; search p95 118 → 121 ms; only a scheduled job releases holds (added to the risk register). ADR-052: groups as a module with an import-boundary check, not the agent's microservice. ADR-053: invoices through the chain-invoicing seam and its golden tests.

    Why: The agent's architecture was research. The decision came from measurements and drivers, with a "revisit if" line.

  3. 3Plan: skeleton, then slices

    Claude Code's first plan was by layer. Reordered: walking skeleton in week 3 (one request → quote → hold → confirmation, one hotel, staging, flag off), then slices: quote approval, holds and expiry, company accounts, monthly invoices, partner rate approval. Pilot in week 7 (10 companies, 30 hotels in Lisbon and Madrid). Estimates as ranges.

    Why: Every slice works end to end, so integration surprises arrive in week 3, not week 12.

  4. 4Rules that hold

    src/groups/CLAUDE.md (golden path, test command, boundaries); holds in src/inventory are stop-and-ask, with CODEOWNERS and a hook that blocks agent edits there; max 2 agent sessions per engineer, each on its own branch or worktree; required checks with no admin bypass, including golden invoice tests.

    Why: Week 6 tested it: a session tried to "optimise" hold queries in src/inventory; the hook stopped it, and the change went to the inventory owners as a proposal.

  5. 5Deliver and report

    Weekly status on outcomes: hill chart per slice, top risks, decisions needed. Week 5: one week behind on quote approval. You keep the WIP cap, move multi-city requests after the pilot, add contract tests between groups and billing. Pilot on time in week 7.

    Why: Scope moved, gates didn't, and Karim read about the slip in Monday's update, not in a corridor.

  6. 6Go/no-go and ramp

    Week 10: pilot quoted 74% within 1 h for two weeks (criterion ≥ 70%), zero invoice differences, kill switch rehearsed, but no on-call owner in the runbook. No-go for one day; owner named; go. Ramp 30% → 60% → 100% of companies, each step on the outcome dashboard.

    Why: Criteria from week 1 weren't bent: the cheap missing one was met, the met ones weren't moved.

  7. 7Incident and retrospective

    At 30%: 1,900 room-nights held by expired quotes in Lisbon (the expiry worker had failed to deploy; no heartbeat). Kill switch first; closed in 40 minutes. Week 13 result: 76% quoted within 1 h, 164 companies invoiced, zero invoice differences. Retro: three actions with owners: read-time expiry in the golden path, heartbeat on every scheduled job, "jobs monitored" in the go/no-go template.

    Why: The risk noted at the spike came true; the kill switch from the criteria contained it; the retro turned it into rules for every future project.

The whole thing in one line: You turned an email backlog into a measured goal, made the one-way-door decisions from a spike, planned slices that worked end to end from week 3, set rules the tools enforced, kept delivery within review capacity, launched on criteria written in week 1, contained an incident in 40 minutes, and ended with an honest number and three owned changes.
StageEvidenceWhat it caught
BriefNumbers, drivers, non-goals, go/no-go, agreedA quarter with no way to judge success
Spike + ADRsMeasurements; ADR-052, ADR-053An unneeded microservice and database; the silent-job risk
PlanSkeleton in week 3; slices with rangesIntegration surprises pushed to the end
RulesCLAUDE.md, hook, CODEOWNERS, required checksAn agent editing inventory holds
DeliveryWeekly status, WIP cap, contract testsA one-week slip, handled by moving scope
Go/no-goCriteria checked by named peopleNo on-call owner
Retro3 actions with owners and datesSilent jobs guarding one-way doors
11

Visual diagram

Click a component

Group & corporate bookings: what you lead, and where the one-way doors are. Click a component, or follow the walkthrough.

12

Analogy

  • Leading a mountain expeditionSummit, date, all safeLeading the projectGoal as numbers
  • Leading a mountain expeditionScout the dangerous passLeading the projectSpike, then decide
  • Leading a mountain expeditionCamps along the routeLeading the projectMilestones and slices
  • Leading a mountain expeditionRope up on glaciersLeading the projectEnforced rules and checks
  • Leading a mountain expeditionSummit push or turn backLeading the projectGo / no-go
  • Leading a mountain expeditionDebrief afterLeading the projectRetrospective

Where it breaks: an expedition ends at the summit. A product keeps running after launch, so the alerts, owners and runbooks have to stay.

13

Why it matters

With agents, a team can produce a lot of code very fast. That's the danger.

Speed amplifies direction. A wrong choice in week 1, built by a dozen agent sessions, becomes a lot of wrong code by week 3.

People set the pace, not agents. Eight engineers can only review so much. More sessions just means a longer queue.

The goal is a number. Guests and companies don't care how many features shipped. They care that a quote now takes an hour, not four days.

14

Check your understanding

Q1/3Reasoning
Put the stages of leading the quarter in order.
  1. 1.Retrospective with owned actions
  2. 2.Brief: goal as numbers, drivers, non-goals, go/no-go criteria
  3. 3.Go/no-go, ramp, incident response
  4. 4.Spike the riskiest unknown; ADRs for one-way doors
  5. 5.Plan: walking skeleton, then vertical slices and agent-sized tasks
  6. 6.Rules: CLAUDE.md files, hooks, permissions, required checks
  7. 7.Parallel delivery within review capacity; weekly status
How confident are you?
15

Practice ladder

Step 1 · Trace

Which stage would have prevented it?

Debugging Warm-up

Another company's quarter-long project, built by agents, went badly. For each event, trace which stage of the leadership loop would have prevented it, and how.

  1. In week 11 the team discovered the payment provider couldn't split invoices by company department, a core requirement.
  2. Nothing worked end to end until week 10; the first full run failed in four places.
  3. An agent session refactored a shared pricing module "while it was there"; another team's tests broke for two days.
  4. Twelve agent sessions ran in parallel; PRs waited five days for review, then were approved in bulk.
  5. The CTO learned of a six-week slip from a customer.
  6. After launch, a cleanup job stopped silently; the same kind of failure had happened in their previous project.
Step 2 · Complete

Complete the go/no-go

Design Practice

Complete the go/no-go section of the group bookings brief, written in week 1.

  • Outcome in pilot: ≥ ___% of requests quoted within ___ for ___ weeks
  • Money: zero unexplained ___ differences against the ___
  • One-way doors: ___ for holds rehearsed; no expired hold older than ___
  • Operations: ___ written; ___ owner named; ___ for every scheduled job
  • Ramp after go: ___% → ___% → 100% of companies, each step decided on the ___ dashboard
  • Who decides: ___, after checking each line with ___
Step 3 · Solve

Lead the next quarter's first two weeks

Design Stretch

Next quarter: Long stays. Guests book 28+ nights at monthly rates; hotels want a deposit and a charge every month instead of one payment. Today ~300 long-stay bookings a month, mostly arranged by email; 1 in 5 has a payment problem.

Without help, write what you'd produce in weeks 1–2: (1) the goal as numbers, (2) four drivers and two non-goals, (3) the spike question for Claude Code with its time box, (4) the ADR question it informs, (5) the walking skeleton, (6) the top three risks with owner and trigger, (7) three go/no-go criteria.

Step 4 · Decide

What next for group bookings?

Decision Stretch

Week 13 results:

MetricTargetResult
Requests quoted within 1 business hour80% (baseline ~5%)76%
Companies invoiced monthly150164
Invoice differences00
Requests still quoted by handnone set18% (multi-city events)

Karim offers two options for next quarter: (A) keep all three squads on group bookings to reach 80%, add multi-city requests and travel policies; (B) hand group bookings to one squad (multi-city requests only, the cause of most manual quotes) and start Long stays with the other two.

Write your decision: "We chose X over Y because…, accepting the risk of…".

16

Explain it yourself

A friend asks: "If AI agents write all the code, what does a tech lead on a big project actually do all quarter?" Answer using the group bookings project.

0 words